Inquiry confirms $7 million overspend on Dixon Hall supportive housing project

Andre Bermon –

 New information has emerged on the controversial support­ive housing project under con­struction at 502–508 Parliament Street.

In late September, Ward 13 Councillor Chris Moise submit­ted an administrative inquiry to Council seeking an update on delays and costs associated with the Cabbagetown project’s 42 affordable rental units.

According to the response by Housing Secretariat execu­tive director Doug Rollins, the original costs were estimated at $7.81 million in 2021, not $6.43 million as the bridge previously reported. Information received from city staff had included only interior renovation costs, not the exterior restoration esti­mate of $1.38 million.

As of this fall, Rollins and Dixon Hall, the non-profit over­seeing the supportive housing project, pegged total costs at $14.97 million, a $7.16 million overrun from the initial budget.

Structural repairs and up­grades to fire and life safety sys­tems are expected to cost $11.5 million, exceeding the original estimate by $5.2 million. The sanitary line replacement has also seen a sharp increase, ris­ing from $113,000 to just over $1 million.

Minutes of an August 2024 meeting the bridge received, revealed the site’s 19th-century sanitary piping needing to be ripped out and replaced. Renovation had started in 2022 and the unanticipated job was expected to add a delay of 14 to 18 weeks.

Heritage revitalization, a key component to this Cabbagetown project, was initially budgeted at $1.37 million, but current es­timates allow $2.24 million.

City officials point to pandem­ic-era construction inflation, dilapidated building conditions and extensive work needed to meet building and fire code standards as reasons for the project’s mounting costs and de­lays.

Through various funding schemes, including $6 million of Section 37 funds, the city has committed $13.6 million so far. This leaves a funding gap of about $1.37 million, which Dix­on Hall states is currently be­ing worked out with the city to “ensure that the project remains fully funded and sustainable.”

The original project scope was revised to exclude the in­terior work at 502 Parliament and its 11 housing units due to limited funds. According to an email statement from Dixon Hall to the bridge, subsequent funding of $4.45 million from the Canada-Ontario Communi­ty Housing Initiative, received in 2024, allowed the interior renovation contract for 504, 506 and 508 Parliament to proceed, as well as a portion of 502’s in­terior restoration. Dixon Hall confirmed that the contractor, TERCO Construction Ltd., used 502 Parliament as the site office and material storage location in the years before its restoration work.

According to the city, 504–508 Parliament is projected to house tenants before the end of this year while 502 Parliament will take until autumn 2026. The original completion date, according to a Freedom of In­formation document the bridge received, was to be December 31, 2021.

Following the adoption of City Council’s Tenant First di­rective in March 2018, Toronto Community Housing Corpora­tion (TCHC) began transferring its 22 rooming house properties to non-profit housing providers. Under this initiative, the city committed to paying for repairs and renovations before transfer­ring the properties.

Dixon Hall, as the future own­er and operator of the Parliament Street site, was responsible for managing onsite construction, including selecting contractors. The agency was also selected to operate another row of TCHC-owned rooming houses in Cab­bagetown, at 265–275 Wellesley Street East. These properties have been boarded up for years, plagued by persistent structur­al and maintenance challenges. Despite plans for renewal, the city has yet to provide funding.